The Oregon lien notice that only looks back 8 business days

Oregon's Notice of Right to a Lien protects materials delivered from 8 business days before the notice is given. Send it three weeks into a job and the first deliveries can sit outside it.

So we'd send it at the start of every Oregon job, commercial ones included if you're a material-only supplier. It goes to the owner in person or by registered or certified mail, unless the owner ordered the materials. A copy to the mortgagee within 8 business days after delivery keeps priority over a recorded mortgage.

Then the counting. Take the earlier of your last delivery and completion of construction, add 75 days, and that's your recording deadline. The worked example on our guide: last delivery March 4, 2026, construction finished after that, record by May 18, 2026. If construction finishes while you're still delivering, the clock starts at completion.

Recording starts more clocks:

Our page on how to count Oregon lien deadlines lists the ORS sections behind each step.

Made with ShipPage ยท HTML in. URL out.